CANADIAN RAILWAY OFFICE OF ARBITRATION
& DISPUTE RESOLUTION
CASE NO. 4011
Heard in
Concerning
CANADIAN PACIFIC RAILWAY COMPANY
And
TEAMSTERS
MAINTENANCE OF WAY EMPLOYEES DIVISION
DISPUTE:
Claim on behalf of B&S employees.
JOINT STATEMENT OF ISSUE:
In or about
April 2010, the Company informed the
The
The
The Company
denies the Union’s contentions and declines the
FOR
THE
(SGD.) WM. BREHL (SGD.) M. CHERNENKOFF
PRESIDENT ASSISTANT
LABOUR RELATIONS OFFICER
There appeared on behalf of the Company:
M. Chernenkoff –
Assistant Labour Relations Officer,
M. Goldsmith –
Labour Relations Officer,
S. Smith –
Labour Relations Officer.
There appeared on behalf of the
Wm. Brehl –
President,
D. W. Brown –
Counsel,
A. R. Terry –
Vice-President,
A. Della Porta – Director, Lachute
AWARD OF THE ARBITRATOR
The
Prior to June
of 2010 had two buildings in Field, the station and the bunkhouse. It is common
ground that the train crew booking in room was located in the station.
Commencing in 2008 concern arose with respect to mould and asbestos in the
station building, a concern which culminated in its eventual closure, with the
decision being made to move the booking in room into the bunkhouse by late
2009. Because the bunkhouse is obviously a place of rest, it became problematic
for the Company to contemplate housing running trades employees in it while the
renovation construction was under way. It therefore became necessary to vacate
the bunkhouse while the renovations were being performed. Additionally, at the
same time it was decided to perform additional renovations, including the
changes to the locker room and bedrooms, painting the interior and exterior
walls, re-carpeting the entire building and removing and replacing concrete
sidewalks outside the building. It appears that the Union was advised of the
Company’s intention to contract out the bunkhouse renovations in January of
2010 in a general sense, gave a specific contracting out notice to the Union’s
Director, Pacific Region, Mr. Henry Helfenbein on April 7, 2010 and commenced
the work two months later, on June 7, 2010. It appears that the
The work here in dispute was performed between June 7 and June 28, 2010. The Company does not deny the Union’s claim that a considerable amount of the renovation work performed is work “presently and normally performed by employees” in the bargaining unit” within the meaning of section 13.2 of the collective agreement which prohibits contracting out, save under certain exceptions.
The Arbitrator
is satisfied, on the basis of the unchallenged submissions of the Company, that
time was of the essence in performing the work in question. As the bunkhouse
could not be used, it became necessary to transport running trades employees to
Lake Louise to stay at either the Lake Louise Inn or the
The position of the Company is that the B&S employees who have performed work of the kind involved in the renovation, who are based at Revelstoke, were fully engaged in their own scheduled duties over the spring and summer months and could not be freed to perform the bunkhouse renovation on the tight schedule which was contemplated. In the employer’s view their regular tasks, involving culvert work, bridge maintenance, building maintenance, fuel stand maintenance and switch heater maintenance kept them fully occupied and unavailable to perform the work which was contracted out in relation to the renovations of the bunkhouse at Field, B.C. The Company also notes that the complement of the B&S department in that location was short of two employees, one of whom was a lead hand bench carpenter whose position was not filled until September of 2010. Apart from their spring and summer duties, all fourteen Revelstoke B&S employees were absent for close to 1,000 hours between May and August of 2010 for annual vacation. The Company also notes that the bargaining unit could not have performed the electrical work which was done by an electrician on a contract basis.
In the circumstances the Company pleads the exceptions found on section 13.2 (a), (b), (c) and (e) of the collective agreement which allow contracting out in the following circumstances:
13.2 Work presently and normally performed by employees who are subject to the provisions of this wage agreement will not be contracted out except:
(a) When technical or managerial skills are not available from within the Railway; or
(b) Where sufficient employees, qualified to perform the work, are not available from the active or laid-off employees, and such work cannot be delayed until such employees are available; or
(c) When essential equipment or facilities are not available and cannot be made available at the time and place required (i) from Railway-owned property, or (ii) which may be bona fide leased from other sources at a reasonable cost without the operator; or
…
(e) The required time of completion of the work cannot be met with the skills, personnel or equipment available on the property; or
The
In the Union’s view the instant case is at all fours with the decision of this Office in CROA&DR 3874 which involved the contracting out of work on a motel converted into a bunkhouse at Hardisty, Alberta. Its representatives suggest that the success of that grievance should indicate the merit of the instant case, where work close to identical to that which was found to be improperly contracted out in that case has again been contracted out in relation to the Field bunkhouse.
In the
Arbitrator’s view the case is not as cut and dried as the Union would have it,
although there is a degree of merit to the
On a close
examination of the evidence, I am satisfied that there obviously was an urgency
to the project, particularly as regards the completion of the interior of the
bunkhouse to restore it an inhabitable space. I consider it noteworthy that the
Company did alter its plan and ultimately has indicated to the
With respect to
the balance of the work, the Union’s position is tantamount to saying that the
Company is compelled by the terms of the collective agreement to have scheduled
the renovation work on the bunkhouse at Field so that much of its construction
would depend on overtime hours worked by bargaining unit members. With respect,
I find that submission less that compelling. While there may be some projects
which can be properly and reasonably be done by employees on a reasonable
overtime basis, given that virtually all of the Revelstoke B&S employees
were fully engaged at the time of the work which is here under consideration,
engaged in tasks critical to the maintenance of the railway’s vital operations
in the mountains of Alberta and British Columbia, I find it difficult to
conclude that the exceptions to the contracting out provisions of section 13 of
the collective agreement can be said to have no application, as the Union
suggests. The case at hand is not, in my view, directly comparable to that
found in CROA&DR 3874 involving
the bunkhouse at
It weighing the
application of the exceptions to the contracting out prohibitions in section 13
it is trite to say that each case must turn on its own particular facts. Of
paramount significance in the case at hand is that the Company was compelled to
vacate the bunkhouse and incur the extraordinary costs of transporting and
housing running trades employees in
May _________, 2011 _______________________________
MICHEL G. PICHER
ARBITRATOR